Palouse Habitat Update for 11.29.2021 with picture from November 20th of laying pavers for the Hansen home front porch:


Construction/Home Repair:
Good evening all;
There are three scheduled work days this week.
Wed 1 Dec: We’ll leave from the south warehouse at 0900 and go to Endicott where we will retrieve a wooden ramp we installed a year ago. From there we’ll continue to Malden where we will install a ramp using the parts from Endicott plus a couple of new parts. It will be a full day, but we expect to be done by 1600. Bring your lunch.
Thurs 2 Dec: At Uniontown we will pour concrete for the Hansen driveway and sidewalk at 0900, so come a bit early if you can. Once that is completed we will also wrap up in the Leaseburg home and continue on the Hansen home exterior. Lunch on our own.
Sat 4 Dec: Work starts at Uniontown at 0900. We’ll continue work on the Hansen home and final wrap up in the Leaseburg home so that cleaning crews can prepare for the dedication of the Leaseburg home on 18 Dec. We are all invited and details will be forthcoming. Lunch will be provided thanks to Kathy Slinker.

Surplus Sale – Reopening Wednesday after being closed last week for the holiday to give our volunteers a break! Open normal hours Wed-Sat 10 AM to 5 PM at 304 North Main in Moscow for shopping and donating.

Habitat office open normal hours Monday-Friday 10:30 to 2:30 PM at 306 North Main in Moscow.

If you’re looking to give meaningful gifts this holiday season, check out the Alternative Giving Market of the Palouse going on now – give to Palouse Habitat and 29 other local nonprofits online at agmpalouse.org or plan on attending the in-person event on December 11th.